Three-Point Estimation for Software Testing Projects

A practical, math-light way to turn uncertainty into a defendable testing estimate—complete with formulas, examples, and how to present P50 vs P80 timelines.

Reading time: ~12–16 minutes · Updated: 2025

Testing estimates fail when we pretend there’s a single “correct” number. Real projects have variability: flaky test data, changing requirements, and environment hiccups. Three-Point Estimation acknowledges that uncertainty and turns it into a simple, defendable number you can present to stakeholders.

New to estimation methods in general? See the big picture in Test Estimation Techniques: Complete Guide (With Examples & Tools) , then come back here to apply the Three-Point math.

How TestScope Pro helps: Import your WBS (CSV/Jira), capture O/M/P with historical hints and outlier alerts, auto-calc PERT, apply risk multipliers, and one-click simulate P50–P90 timelines. Capacity calendars (meetings/holidays), an Assumptions Manager, and an exportable “Estimate Defense Pack” make reviews painless.

What Is Three-Point Estimation?

For each task, you provide three effort values:

  • O (Optimistic): Best case if things go smoothly.
  • M (Most Likely): Realistic expectation based on experience.
  • P (Pessimistic): Realistic worst case (not catastrophic failure).

The result is a weighted average that reflects uncertainty—far better than a single guess.

In TestScope Pro: O/M/P fields show guardrails from your past releases and flag values that look inconsistent with similar work.

Why QA Teams Use It

Pros

  • Captures uncertainty simply (no heavy statistics required).
  • Easy to explain to leadership and cross-functional partners.
  • Pairs well with WBS, risk weighting, and calendar capacity.

Limitations

  • Quality depends on realistic O/M/P inputs.
  • Doesn’t show probability of hitting a date by itself (use Monte Carlo for that).

TestScope Pro’s “What moves P80?” view pinpoints the tasks that most affect confidence so you can de-risk, not just pad.

Formulas (Triangular vs PERT)

Triangular Average

Estimate = (O + M + P) / 3

Simple, equal weight to each input. Useful for quick back-of-the-envelope sizing.

PERT-Weighted Average

Estimate = (O + 4M + P) / 6

Gives more weight to “Most Likely,” reducing the influence of extreme values.

In TestScope Pro: Toggle Triangular/PERT per task (default PERT). Variance and roll-ups update instantly.

Step-by-Step: Applying It to Testing

  1. Start with a WBS. Break testing into 4–16 hour tasks (design, data, execution, triage, regression, non-functional, reporting).
  2. Capture O/M/P per task. Use historicals or expert judgment; note assumptions (“staging data ready”).
  3. Compute PERT per task. Use (O + 4M + P)/6.
  4. Sum PERT across tasks. That’s your total effort hours (P50-ish center of mass).
  5. Convert to calendar time. Divide by weekly QA capacity (testers × focus hours).
  6. Present confidence levels. Derive P80/P90 as “confidence buffers” (or run Monte Carlo).

In TestScope Pro: Import WBS → enter O/M/P → apply risk multipliers by module/platform → click Simulate for P50/P80/P90 dates → export the review deck with assumptions & change log.

Need a refresher on the broader toolkit? See the complete estimation guide .

Worked Examples

Example A: Regression Cycle

Inputs: O=40h, M=60h, P=100h

PERT: (40 + 4×60 + 100) / 6 = 63.3h

Interpretation: Plan ~63 hours for this task; use it in your roll-up.

Example B: Test Design for a New Checkout

SubtaskOMPPERT
Boundary & negative cases4814(4+4×8+14)/6=8.3
API contract tests61016(6+4×10+16)/6=10.7
Data design & fixtures3612(3+4×6+12)/6=6.5
Total~25.5h

Example C: Risk-Weighted Module Mix

ModuleRiskOMPPERTRisk FactorAdjusted
PaymentsHigh20304831.31.3×40.7
ProfileLow10162416.30.9×14.7
NotificationsMedium8122012.71.0×12.7
Total~68.1h

In TestScope Pro: The “risk heat” overlay highlights rows that contribute most to P80 slip so you can propose precise tradeoffs.

From Hours to Calendar Time (Capacity)

Capacity Formula

Weekly QA Capacity = Testers × Focus Hours/Week

Example: 3 testers × 30 focus h/wk = 90 h/wk

Duration

Duration (weeks) = Total PERT Hours / Weekly QA Capacity

Example: 215 h / 90 = 2.4 weeks

If different streams can run in parallel, compute each stream’s duration and take the maximum.

In TestScope Pro: Capacity calendars account for meetings/holidays, SDET vs QA mix, and parallel streams—your dates update live as you tweak staffing.

P50 vs P80: Presenting Confidence Without “Padding”

  • P50: The central estimate (sum of PERTs). You’ll hit it about half the time.
  • P80: A more conservative plan that accounts for variance in high-risk tasks (often P50 + 10–20%).
  • P90: For critical launches; use sparingly (P50 + 20–35%).

Prefer data over flat percentages? Run Monte Carlo on your O/M/P—TestScope Pro produces executive-ready P50–P90 range bars with assumptions.

How to pitch it: “P50 is 2.4 weeks; P80 is 2.9 weeks with the current team. Which confidence level would you like to fund?”

Combine with WBS & Monte Carlo

WBS gives you transparency into where time is going. Three-Point/PERT captures uncertainty. Monte Carlo turns those ranges into probabilities (P50/P80/P90) across the whole project, especially when many tasks interact.

In TestScope Pro: WBS → O/M/P → Simulate → export “Estimate Defense Pack” (WBS summary, assumptions, risk heatmap, P-level timelines).

For a broader toolkit and when to pick each method, see Test Estimation Techniques: Complete Guide .

Common Pitfalls & How to Avoid Them

  • Unrealistic O/M/P: Calibrate with historicals; document assumptions (env parity, data readiness).
  • Forgetting hidden work: Include environment/data, defect cycles, meetings, automation maintenance.
  • “Single number” syndrome: Always present ranges (P50/P80) with risks and dependencies.
  • No re-estimation: Re-run when requirements change or risks materialize.

TestScope Pro guardrails: Outlier detection on O/M/P, required assumptions on risky rows, automatic change-log and version diff for re-estimates.

Copy/Paste Template

TaskOwnerO (h)M (h)P (h)PERT (h)Notes/Assumptions
Test strategy & planQA Lead61016(6+4×10+16)/6=10.7Exit criteria agreed
Test case/charter designQA Eng20325234Boundary & negative included
Environment & data setupQA/DevOps8122013Staging parity; anonymized snapshot
Functional execution (UI/API)QA Eng508012085Exploratory sessions planned
Non-functional (perf/a11y)Perf/A11y10183018.7p95 targets, WCAG AA
Defect triage & verificationQA Lead16244025Daily triage cadence
Regression & sign-offQA Eng16243624.7Automation maintenance included
Total~211.1h

Paste into a sheet—or import CSV into TestScope Pro to simulate P50–P90 calendars and export the stakeholder-ready pack.

FAQ

Is Three-Point the same as PERT?

Three-Point is the input model (O/M/P). PERT is a weighted way to combine them, giving extra weight to the “Most Likely.”

How do I pick O/M/P values?

  • Use historicals where possible (similar modules or past releases).
  • Ask two experts independently, then reconcile (Delphi style).
  • Write explicit assumptions so inputs aren’t wishful thinking.

How do I communicate the result?

Publish P50 and P80 timelines with assumptions, risks, and scope. Invite stakeholders to choose the confidence level based on business risk.

Conclusion & Next Steps

Three-Point Estimation is a practical middle ground between guesswork and heavy statistics. It helps QA leaders produce estimates that reflect uncertainty, convert cleanly to calendar time, and stand up to scrutiny.

For a tour of complementary methods (WBS, analogous, risk-based, Monte Carlo), check out Test Estimation Techniques: Complete Guide (With Examples & Tools) .